Mallorca wetland drilling: firm accused of no licence

Responsible for this content: Frank Menze

Mallorca’s Maristany wetland near Alcúdia is at the centre of a drilling dispute: a local group says a Red Eléctrica subcontractor began work there in June without a council licence. Red Eléctrica had said the work had all the required permits. The wetland is specially protected for birds and forms part of the Natura 2000 network.

Acusan a Red Eléctrica de perforar en Maristany sin licencia pese asegurar que tenía 'todos los permisos'
Europa Press

What the council papers show

On 11 June, before drilling began, Red Eléctrica said it had the necessary permits. On 16 June, an environmental officer from the Balearic government stopped the drilling and recorded an infringement. The company said the dispute arose from differing interpretations of the birds’ nesting season and maintained that it had acted with the required authorisation.

The Association for a New Agreement on the Alcúdia Cable, known as Anaca, says Alcúdia council gave it access to the drilling files. According to the group, a council inspector’s report dated 18 June found that one drilling operation had begun in a coastal protection zone without the required council authorisation.

A separate permit to drill in the wetland and on public waterways was still being processed on 14 August, according to the Balearic government. It did not reach the council until 17 August.

A licence request remains open

Red Eléctrica notified the council of the drilling on 27 August. The council ruled that notification ineffective and ordered any work already begun to stop immediately. The company applied for a works licence for the same drilling on 14 September; that application remains under consideration.

Anaca also alleges that the subcontractor entered private land without warning or the owners’ permission. One owner asked the authorities on 20 June whether any company had sought permission to drill on their property.

Those affected plan to join the licence process to oppose the drilling, according to Anaca. They also intend to bring the matter before the Territorial Defence Agency and inform Spain’s Ministry for the Ecological Transition as part of a legal challenge.

Topics: Environment · Palma · Alcúdia

Source: Europa Press / Mallorca.com